Runoff Recharge: DPW Office Building, Westborough
All parking lot and rooftop runoff from the new
DPW office building will discharge to landscaped swales and infiltration
units. The system has been equipped with Cultec oil/water separators
and sediment sump catchbasins to trap pollutants from the parking
lot. The project has a total of 22,500 sq. ft. of impervious surface.
The Project funded the addition of the swales, filters and infiltration
units located under the parking lot. The previously disturbed site
had drained to a nearby wetland which is hydrologically connected
to the Assabet River and its tributary Juniper Brook. The project
is scheduled for completion in 2006.
Method used: Roof drainage redirected
to two infiltration units
Sub-watershed: Juniper Brook, Assabet River
headwaters
Recharge estimate: 540,000 gallons of water
per year
(15,000 gal. per storm event; daily average rate 1,500 gal.) plus
infiltration through the grassed swale
Intel grant: $50,000 for materials
and design
Town contribution: engineering and
construction services
Location: 131 Oak Street, Westborough
Contact: Carl
Balduf, Town Engineer, Tel: 508-366-3070
|